The office build-out budget is determined by the conditionof the leased space and the number of private rooms required. It also dependson how much your landlord contributes and how long your approvals take.Square-foot averages hide all four.
The budget is broken down into the line items that willactually be paid, and how a tenant improvement allowance works is explained inthis guide. The costs that are often missed by first-time tenants are alsohighlighted, including those added by Orange County cities, landlords, andbuilding codes.
An open-plan start-up floor and a law office full of privaterooms are treated as the same project by a single cost-per-square-foot figure.They are not.
Very different amounts can also be paid for the same suite,depending on whether a finished office is inherited or the project is startedfrom a bare shell. Any average that is found should be used as a rough screen,and then it should be replaced with a bid based on your own plans.
Know Your StartingCondition
The baseline for everything else is set by the spacecondition. Walls, ceilings, and restrooms have already been built by a priortenant in second-generation space. If your layout is like theirs, you can makeuse of most of the effort already put in and simply finish the job. However, ifyour layout is quite different, then besides the cost of building, you willincur extra costs for demolition as well.
Shell space is delivered by the landlord with concretefloors, exposed structure, and basic building systems. You build everythinginside. Shell gives you design freedom and the highest construction scope.
Buildings which have an older mechanical, electrical, andfire system will require upgrades when the permit authorities check yourmodifications. The space should be walked with your contractor before the leaseis signed, not afterward.
Hard costs cover the physical construction. A typical OrangeCounty office build-out includes the following categories. Demolition andframing include removing old walls and building new ones.
The ceiling, drywall, and paint have quality of finish,which has greater effect on this line than square footage. The flooringconsists of carpet tile, luxury vinyl, polished concrete, and hardwood, all atvery different price points.
Doors, glass and millwork consist of glass-front offices andcustom-built reception desks, both much more expensive than solid core doorsand laminate counters. Mechanical, electrical, and plumbing involve moving ofair conditioning ductwork and adding electrical circuits.
The break room or server room could also consume a lot fromthe budget. Each of the private offices would need their individual airconditioning and lighting controls. Fire Sprinklers and Fire Alarms systemshave movable sprinklers and alarms where walls have been moved. Systems such aslow voltage systems have movable data cables, access control, and AV wires.
Private offices are more costly than open desks. Walls, adoor, lighting, ventilation, and sprinkler coverage are added with eachenclosed room. To control costs, the count of enclosed rooms should be reducedbefore finish quality is reduced.
Soft costs are not included in your contractor's bid, andfirst-time tenants are often caught off guard by them. Design & Engineeringincludes architects, interior designers, and MEP Engineers. Permits and PlanReview Fees are levied by the city where your building stands.
Furniture, fixtures, and equipment (FF&E) includesdesks, chairs, conference table furniture, and kitchen appliances in breakrooms. IT and Telecom includes internet circuits, network equipment,telephones, and conferencing technology. Landlord and city permissions aresometimes required for signage for suite and building signs.
Relocation costs will include rental payments at yourcurrent location even as you build the new one. Legal review includes lease andconstruction-contract review. Budget soft costs in a separate column from hardcosts. Owners who blend them lose sight of how much money actually goes toconstruction.
A tenant improvement allowance (TI allowance), a dollaramount per square foot, is offered by many landlords toward the build-out.Reimbursement is usually provided after invoices and lien releases aresubmitted, rather than a lump sum is being provided at signing. The allowancerarely covers everything, so treat it as a discount on your budget, not thebudget itself.
Three details in the lease should be read before you counton the money.
The allowance can pay for different costs, as some leasescover only hard costs, while others also cover design fees, cabling, or movingcosts. Whether the landlord amortizes extra money depends on whether more thanthe base allowance is advanced.
The extra amount is recovered through higher rent over thelease term. This will lower your initial costs but increase your overalloccupancy cost. The control over the task differs, with some landlordsrequiring you to hire their contractor and others charging a supervision fee.Both choices affect price.
A larger allowance does not always outweigh a lower rent.The two should be compared over the full lease term, and both should be modeledby your broker before a decision is made.
City-by-CityPermitting
No single permit office is provided for Orange County. Eachcity has its own building department, with its own fees, submittalrequirements, and review times. Its own requirements are followed by citiessuch as Irvine, Newport Beach, Costa Mesa, Santa Ana, and Anaheim.
The actual plan-check turnaround at your building's cityshould be requested from your architect. Your schedule and overlapping rent aredriven by that number.
State CodeRequirements
California's Title 24 energy standards affect officeinteriors. Lighting layouts and controls are usually required to meet currentenergy requirements. Additional compliance documentation can be triggered bychanges to mechanical systems.
Accessibility rules in the California Building Code can alsorequire upgrades to restrooms, entrances, or the path of travel. These upgradescan be required when certain cost thresholds are reached by your project.
Landlord and BuildingRules
Building rules cost real money even though they never appearin code. After-hours work, freight-elevator reservations, certificates ofinsurance naming the owner and approval of your contractor and plans are oftenrequired by landlords.
The building's contractor rules and construction-hourspolicy should be requested during lease negotiation, before the job is pricedby your contractor.
Lease-End Restoration
Your improvements may be required to be removed, and thespace may be required to be restored when the lease ends. If yours does, thatfuture cost belongs in your decision today, particularly if you plan to buildglass offices, a specialty room, or heavy cabling.
How to Build aRealistic Budget, Step by Step
List your needs through counting head count, private officespace, conference room, and special room, such as server room or laboratory.Ensure the landlord puts down on paper your lease term including the allowanceand landlord’s construction specifications.
Hire an architect to do a test fit to see if the program canbe accommodated within the space. Ask at least two contractors for their pricesusing the same plans and scope of work for comparison purposes. Add soft costsseparately by including design, permits, FF&E, IT, signage, and moving.
Set a contingencyline based on the age and condition of the building. Use a smaller amount for arecently finished suite and a larger amount for an older building with unknownconditions. Check long-lead items such as glass frontage, HVAC equipment,electrical equipment, and custom-made furniture.
These items may require longer time to deliver than the timetaken for completion of the construction process. Compare the total cost toyour allowance and lease by deciding how much you pay now and how much youfinance through rent.
Where to Find CurrentPricing Benchmarks
Office fit-out cost guides are published by industrybrokerages and cost consultants. They have been produced in the past by firmssuch as Cushman & Wakefield, JLL, and Cumming. These guides help youcompare markets, but they average many project types. Treat them as a sanitycheck on your contractor's bids, not as a replacement for a bid.
Frequently AskedQuestions
How much does anoffice build-out cost in Orange County?
The answer is determined by your starting condition, thenumber of private offices, your finish level, and your landlord's contribution.A test fit and two contractor bids should be obtained for your specific suite.Those bids will tell you more than any published average.
What is thedifference between a tenant improvement and a build-out?
The terms are used interchangeably. Changes to leased spaceare usually referred to as a tenant improvement, while constructing theinterior of a bare shell is often referred to as a build-out. In both cases, acontractor is hired, permits are pulled, and coordination with the landlord isrequired.
Does the landlord payfor my office build-out?
Only partly, and only if a tenant improvement allowance isincluded in your lease. Approved costs are typically reimbursed by landlords upto a set per-square-foot amount. Anything above that is paid by you, unless anagreement is made with the landlord to recover it through higher rent.
How long does anoffice build-out take?
The timeline includes three phases, including design, permitreview, and construction. The permit review will depend on the time required byyour city to check your plans, and construction will depend on the scope andmaterials. Request a list from your architect and builder indicating thetimeline of each process.
Do I need a permit torenovate leased office space?
Usually yes. Moving walls, changing electrical or mechanicalsystems, or altering fire sprinklers triggers permit review in most cities.Purely cosmetic work such as paint and carpet sometimes needs no permit, butconfirm with your city's building department before you start.
Can I use my owncontractor?
Often, but your lease controls the answer. Some landlordsrequire you to hire from an approved list or use their contractor. Ask for thepolicy in writing before you negotiate the lease.
Final Takeaway
A good office build-out budget is started with the lease,not the construction bid. The allowance, the landlord's rules, and the startingcondition of the space should be locked down first. The work should then bepriced with real plans, soft costs should be added separately, and acontingency sized to the building's age should be held.